In-Situ Concrete & Power-Floated Floors
Reinforced slabs, power-floated floors, machine bases and external hardstanding — set out, reinforced, poured and finished by our own crews, as part of the groundworks package rather than a separate trade to co-ordinate.
The Short Answer
An in-situ concrete contractor pours concrete wet into formwork in its final position on site, rather than lifting in factory-made units. That covers reinforced floor slabs, pad foundations and machine bases, retaining structures and external hardstanding — set out, reinforced, poured, finished and cured in place.
We erect pre-cast concrete as well, so a package can be split whichever way the design actually wants it. See the full service list, or Section 278 and Section 38 highway works for concrete inside a highway scheme.
What We Pour
The same crews that dig the formation, lay the drainage and prepare the sub-base cast the concrete on top of it — so there is no interface to manage between the groundworker and a separate concrete subcontractor.
Ground-bearing and reinforced slabs, inside and out.
Everything the frame and the plant land on.
Specifying It
The finish decides the programme as much as the slab thickness does. This is the short version of the conversation we have with estimators before a pour is priced.
| Finish | How it is achieved | Typically used for |
|---|---|---|
| Tamped | Tamping beam drawn across the wet surface | External slabs and hardstanding needing grip |
| Brushed | Stiff brush drawn over a floated surface | Ramps, yards and vehicle routes |
| Floated | Skip float or bull float only | Slabs taking a screed or thick build-up on top |
| Power floated | Ride-on or walk-behind float, pans then blades | Warehouse and industrial floors taking a coating |
| Power trowelled | Repeated trowel passes closing the surface | Abrasion-resistant floors under racking and forklifts |
Whatever the finish, the joint layout and the surface regularity class need to be fixed before the first pour. Changing either afterwards means cutting into a slab that has already cured.
Recent Work
A commercial development in Lincolnshire taken from deep drainage and excavation through to reinforced slabs, power-floated internal floors and external hardstanding — one package, one programme.




Common Questions
In-situ concrete is poured wet into formwork in its final position on site and cures there. Pre-cast concrete is manufactured in a factory and lifted into place. In-situ suits slabs, bases and anything that has to fit an existing level or an irregular shape; pre-cast suits repeated units where the lifting plan and the factory tolerance are the advantage.
A dense, closed, hard-wearing surface that takes a coating or line marking directly, with no screed on top. The float closes the surface and the trowel passes burnish it, so the floor resists abrasion from forklifts and racking legs far better than a tamped or brushed finish.
We work to the surface regularity class named in the specification and set the pour, the screed rails and the joint layout around it. The class has to be agreed before the pour rather than after: it dictates the bay sizes, the joint positions and how much slab can be poured in one visit.
Yes, and it is a large part of what we do. We set out and cast pad foundations, pile caps and machine bases with holding-down bolts cast in to the fabricator's template, so the frame goes up on the dates the programme says rather than waiting on remedial grouting.
Yes. Mesh, loose bar, fabric supports, formwork and the joint system are all part of our package, and the same crews that excavate and prepare the sub-base cast the slab. One contractor carries the formation level, the reinforcement cover and the finish.
The slab drawings with levels, the reinforcement details, the concrete specification and the surface regularity class. If there is a joint layout or a floor-loading schedule, send that too — the joints and the loading usually decide the programme more than the volume of concrete does.
Send us the slab drawings, the reinforcement details and the specification — we will come back with a competitive, deliverable price.